The Meridian // Dispatch M008

Data Centers Must Go Below Ground and Off Grid

M008 Data
Americans Opposed to a Local Data Center▲ 71% Projects Blocked or Delayed H1 2026▲ about 120 Investment Stalled H1 2026▲ $198 billion Opposition Groups▲ more than 840 in 49 states Public Comments Opposed▲ 90.5% at 906 meetings Hazle Township Offer■ $45 million – rejected Loudoun Data Center Tax FY2026■ $794.8 million Below-Ground Premium■ about 7% of the project Park Lid per Acre■ $2.2–13.8 million Millennium Park per Acre■ $19.7 million PJM Capacity Cost Tied to Data Centers▲ $6.3 billion of $16.4 billion Ratepayer Protection Act■ passed 417 to 3

Americans are refusing the buildings the AI economy runs on. Put them underground, let them power themselves, and give the town a green and natural park on top.

The Hum in Memphis

In June 2024, xAI began building Colossus, its supercomputer in south Memphis, and started installing gas turbines to run it. In January 2025 the company applied to the Shelby County Health Department for 15 of them. Aerial images taken that April and published by the Southern Environmental Law Center, counsel to the residents who later sued, showed 35 on site.

The county permitted 15 in July 2025. By then an xAI affiliate had bought a former power plant across the state line in Southaven, Mississippi. Mississippi regulators approved 41 turbines there in March 2026, with 27 more running under a temporary exemption. Neighbors less than half a mile away describe a constant hum, and some have moved.

The NAACP sued under the Clean Air Act in April 2026. On 30 October, a federal court refused to dismiss the suit, holding that the Southaven plant "was not (and is not) exempted from permitting requirements."

Memphis is what a data center that generates its own power looks like when it is built in the open, on the surface and ahead of its permits.

The Country Is Saying No

Gallup found in March 2026 that 71 percent of Americans oppose an AI data center in their area, 48 percent of them strongly. A nuclear plant draws 53 percent opposition. The neighbors would sooner have the reactor.

Data Center Watch counted at least 75 projects worth about $130 billion blocked or delayed in the first quarter of 2026, and at least 45 worth nearly $68 billion in the second. Added together, that is about 120 projects and $198 billion stalled in six months. More than 840 opposition groups now operate in every state except Hawaii. At 906 local government meetings tracked by Prophecy Gov, 90.5 percent of public comments opposed the project on the agenda.

Gallup also asked opponents why. Water and the strain on the grid led at 18 percent each, higher utility bills followed at 15 percent, then noise, land, property values and the look of the thing.

A Check Has Not Bought a Yes

Developers have tried paying. NorthPoint offered each of about 4,500 households in Hazle Township, Pennsylvania, $10,000 – $45 million in all – plus $120 million over 15 years. The township rejected the project.

Community benefits agreements run on cash as well. Lancaster, Pennsylvania, secured $20.25 million, a cap on water use, noise limits and setbacks. Columbia Law School's Sabin Center reviewed the agreements in force in May 2026. None includes parkland or public open space.

Loudoun County, Virginia, shows the limit of money most clearly. Data center equipment tax is budgeted at $794.8 million for fiscal 2026, close to 30 percent of the county's local tax revenue. In September, the county directed staff to prepare a 12-month moratorium on new applications anyway.

Mining for Capital Outside AI – $412 Billion Raised, Only $57 Billion Left in the Seams counted 86 percent of US venture money in the first half of 2026 going to AI. The money has arrived. The ground under it has not been granted.

Put the Building Underground

Underground data centers already run. Iron Mountain operates one 220 feet down in a former limestone mine in Boyers, Pennsylvania, cooled from a 100-acre underground reservoir and authorized for federal workloads. Lefdal Mine Datacenter in Norway runs on fjord seawater at a power usage effectiveness of 1.08 to 1.15.

The ground helps. A few feet down, the earth holds a near-constant 40°F to 70°F. The building loses its silhouette and its noise.

What the ground does not do is absorb the heat of a modern campus. Rock conducts too slowly to carry away more than a sliver of 100 megawatts, so the heat rides a water loop to coolers on the surface. In this layout, the coolers and the substation take the edge of the site, the way mechanical plant takes the back of a building, and the roof becomes the park.

Give the Town A Park on Top

The precedent is in West Harlem. In 1968, residents organized against a sewage treatment plant planned for the Hudson riverfront. The state built Riverbank State Park on its roof to answer them – 28 acres with a pool, a skating rink, an amphitheater and athletic fields, drawing millions of visitors a year.

Copenhagen did the same with a power plant. CopenHill burns the city's waste for electricity and district heat, and its roof is a public ski slope.

The town gets more than the lawn. In a review of two decades of studies, John Crompton of Texas A&M University put the premium on homes abutting a passive park at about 20 percent, with the effect reaching 500 to 600 feet. Around Millennium Park in Chicago, condos with park views sell at a 25 percent to 40 percent premium per square foot.

What a Park Lid Costs

A data center needs 5,000 to 12,000 square feet of building for each megawatt, according to the American Planning Association. For 100 megawatts on a single level, that is a footprint of 11.5 to 27.5 acres.

Cushman and Wakefield puts an all-in greenfield build at $8.9 million to $23.3 million per megawatt, with the shell and sitework 17 percent of the total. That 17 percent is the only part going below ground changes.

Nobody publishes a premium for a purpose-dug data hall. The nearest public measure is parking – Rider Levett Bucknall data, reported by UCLA's Institute of Transportation Studies in February 2026, put underground parking at about $73,000 a space against $52,000 above ground, 1.40 times the cost.

Applied to the shell, going below ground adds $60.5 million to $158.4 million per 100 megawatts, about 7 percent of the project. Divided across the roof, the park costs $2.2 million to $13.8 million an acre.

Chicago paid $19.7 million an acre for Millennium Park, built over rail lines and garages and finished in 2004. Dallas paid $22 million an acre to deck Klyde Warren Park over a freeway in 2012. A data hall runs deeper and heavier than a garage, so the parking ratio is a floor. At the costly end of the range, the below-ground premium can rise to 57 percent before the lid costs more per acre than Millennium Park. At the cheap end, it can rise to 358 percent.

Off the Grid and On Its Own Account

The roof answers the eyesore, the land and the noise. Water and power answer the rest.

On power, the fight is already about who pays. PJM's independent market monitor attributes $6.3 billion of the $16.4 billion in its latest capacity auction to data center load, and has recommended moving data centers into an auction of their own. In September, the House passed the Ratepayer Protection Act 417 to 3, setting a standard that loads of 100 megawatts or more pay for the grid upgrades they trigger. Lawrence Berkeley National Laboratory finds the other side as well – the states with the fastest demand growth saw real power prices fall. Whether bills rise depends on rate design. A campus that makes its own power takes itself out of that argument.

In September 2026, the Nuclear Regulatory Commission issued the first US construction permit for a GE Vernova Hitachi BWRX-300, a 300-megawatt small modular reactor at the Tennessee Valley Authority's Clinch River site. Fervo Energy's Cape Station in Utah is delivering 33 megawatts of enhanced geothermal power commercially, with 400 megawatts more under construction for 2028. The Energy Information Administration puts the overnight cost of a small modular reactor at $7,590 per kilowatt and geothermal at $3,403. Gas turbines cost a fraction of that. Memphis shows what they sound like in the open.

On water, Trane's reference design for a one-gigawatt AI campus uses dry coolers that consume no water. The Uptime Institute reported in April 2026 that dry cooling can match or outperform evaporative systems.

The Trade

The next town to hear a data center proposal is weighing a check. The better offer is a building it never sees and a park it gets to keep.

Hazle Township turned down $45 million. Riverbank State Park was the answer West Harlem accepted.

VOR27 Intelligence™ advises the enterprise in the moments that determine trajectory – raise, transaction, market entry – the repositioning that sets the agenda. We convert strategic positioning into measurable outcomes, developing the argument and executing it with discipline, end to end. Companies are rarely limited by the quality of their ideas, especially with the advent of intelligence tools. They are limited by execution.

+$20B client outcomes // +$7B 2025–2026

Sources

Memphis

Opposition and payment

Underground, parks and property

Cost

Power and water

A note on sourcing – figures with a public source page are linked inline. The Memphis timeline comes from the Southern Environmental Law Center, counsel to the residents who sued. The park-lid cost per acre and the breakeven below-ground premium are VOR27 calculations from the cited cost data, with underground parking as the cost proxy. This analysis is informational only. It is not investment, legal or tax advice, and not an offer or solicitation to buy or sell any security.

Connect

Climb. Scale. Win.

The disruption is rewriting every industry. We build the argument that carries you through it, and keeps you in business on the other side.

Message received. Custom reply email inbound.

Every message is read personally. We respond to email, contact form, and phone inquiries immediately during business hours.

+1 646.883.4010